Pritchett Water Reclamation Facility (WRF) Project
Schedule/Status
The Final Notice to Proceed for the Design-Build Contract for the Arbennie Pritchett WRF was issued to CDM on July 2, 2007. Construction and testing of the new WRF is scheduled to be substantially complete within 720 days from this date or by June 19, 2009. The final completion date for the project is September 19, 2009. The other components of the Program will move forward independently of the WRF project and all components should converge to completion with the commissioning of the new facility by the substantial completion date. PDF files of the WRF Project schedule and monthly status report can be accessed at the following links:
» WRF Project Schedule (PDF)
» WRF Contractor Monthly Status Reports:
|