Preparing Outer Digester Wall for Pre-stressing |

Continued Application of Shotcrete onto Clarifier Exterior Wall Surface |

Continued Application of Shotcrete onto Clarifier Exterior Wall |

42-in Return Activate Sludge/Waste Activated Sludge (RAS/WAS) line. |

42” RAS/WAS Line |

View of Construction of Oxidation Ditch #1 from 42” RAS/WAS Line |

Trench for 8” Drain Line for Oxidation Ditch #2 |

Setting Re-bar for Oxidation Ditch # 1 Base Slab |

Re-bar for Oxidation Ditch #1 Base Slab |

QA/QC Check of Re-bar |

Project Sign |

Setting Re-bar for Interior of Clarifier |

Re-bar Set Against Diaphragm Form for Interior of Clarifier |

42” RAS/WAS Line |

8” Drain line for Ox-Ditch #2 |

Forming of Inside Launder for Clarifier |

Re-bar for Inside Lauder or Clarifier |

Setting Vertical Section of 42” RAS/WAS Line |

42” RAS/WAS Installation |

Reclaimed Water Distribution Line for a RIB |

OCWS Crew Setting Reclaimed Water Pipe |

OCWS Crews Setting 30-in Reclaimed Water distribution Pipe for RIBs Project |

OCWS Crews Setting 45s in Reclaimed Water Distribution Lines for RIBs Project |

OCWS Crews Staging 30-in Reclaimed Water Distribution Lines for RIBs Project |

Erecting Diaphragm for Exterior Wall of Digester |

Wall Penetrations to Exterior Wall of Digester |

Clarifier #1 |

Gallery for 42-in Return and Waste Activated Sludge Lines |

Interior of Clarifier |

Base of Digester Exterior Wall |

Preparing Interior of Clarifier Wall for Shotcrete Application |

View of the Site from the Stormwater Detention Basin |

Continued Application of Shotcrete to Digester Exterior Wall |

30-in Effluent lines from the Treatment Plant to the RIBs |

30-in Effluent lines from the Treatment Plant to the RIBs |

30-in Effluent lines from the Treatment Plant to the RIBs |

Erecting Diaphragm for Outer Ring Wall |

Outside Wall and Slab Interface for Oxidation Ditch |

Diaphragm for Oxidation Ditch Exterior Wall |

Vapor Barrier for Oxidation Ditch Base Slab |