County Administrator Jim Curry Addresses Gathering to Celebrate the 50% Complete Milestone for the APWRF |

County Administrator Jim Curry Addresses Gathering to Celebrate the 50% Complete Milestone |

OCWS Director Jeff Littrell Addresses Gathering to Celebrate the 50% Complete Milestone |

Constantine Line Spot Crew Enjoys the 50% Complete Celebration |

Celebration of the 50% Complete Milestone for the APWRF |

Celebration of the 50% Complete Milestone for the APWRF |

Celebration of the 50% Complete Milestone for the APWRF |

Commissioner Jannazo Celebrates with David Kozan and Others at the 50% Milestone Fish Fry. |

Celebration of the 50% Complete Milestone for the APWRF |

Celebration of the 50% Complete Milestone for the APWRF |

Jeff Ogelsby and Ted Hortenstein Celebrate the 50% Complete Mark |
Joey Crews, Kart Vaith and Mark Wise Celebrate the 50% Mark |

Celebration of the 50% Complete Milestone for the APWRF |

OCWS Construction Crew Cooks Up Racks of RIBs to CWS RIBs Project |

OCWS Construction Crew Cooks Up Racks of RIBs to CWS RIBs Project |

OCWS Construction Crew Cooks Up Racks of RIBs to CWS RIBs Project |

OCWS Construction Crew Cooks Up Racks of RIBs to CWS RIBs Project |

Will Coker Waiting on the RIBs |

OCWS Construction Crew Cooks Up Racks of RIBs to CWS RIBs Project |

OCWS Construction Crew Cooks Up Racks of RIBs to CWS RIBs Project |

OCWS Construction Crew Cooks Up Racks of RIBs to CWS RIBs Project |

Yank |

RIB Cake |

OCWS Construction Crew Cooks Up Racks of RIBs to CWS RIBs Project |

OCWS Construction Crew Cooks Up Racks of RIBs to CWS RIBs Project |

OCWS Construction Crew Cooks Up Racks of RIBs to CWS RIBs Project |

OCWS Construction Crew Cooks Up Racks of RIBs to CWS RIBs Project |

Waiting on the RIBs |

Jeff Littrell, Jeff Ogelsby, and Jim Kizer Give Presentation on the OCWS RIBs Project |

Jeff Littrell Brags on the OCWS Construction Crew |

Waiting on the RIBs |

Overhead Electrical Conduit at the Garniers Re-Pump Station (GRPS) |

Suction Lines and Plug Valves for the GRPS |

Suction Lines and Plug Valves for the GRPS |

Suction Line and Plug Valve at the GRPS |

Suction Line at the GRPS |

Motor and Pump at the GRPS |

Installing Check Valve at the GRPS |

Check Valve |
 |

Yard Piping at the GRPS |

Gutters and Downspout Installation at the GRPS |

Ceiling Installation at the Garniers Re-pump Station |

Ceiling Installation at the Garniers Re-pump Station |

Plug Valve Installation t the GRPS |

Roofing the Administration Building at the APWRF |

Roofing the Admin Building at the APWRF |

Maintenance Building at the APWRF |

Digester and Rotary Drum Thickener at the APWRF |

Electrical Building APWRF |

RAS/WAS Pump Station APWRF |

Headworks APWRF |

Electrical Building #2 APWRF |
|

The Garniers Re-Pump Station |

Setting Pump 2 at the Garniers Re-Pump Station |

Setting Pump at the GRPS |

Installing Cement Board at the GRPS |

Setting Pump 2 at the GRPS |

Suction Lines at the GRPS |

Discharge Line at the GRPS |

Applying Textured Finished to Cement Board in the Electrical Room GRPS |

Suction Line for Pump 3 GRPS |

Exterior Work GRPS |

The GRPS |

Exterior Finish Work GRPS |

Exterior Work GRPS |

Workmen at the GRPS |

Setting Suction Line at the GRPS |

Finishing Walls of the Electrical Room GRPS |

Interior Walls of GRPS |

Generator Set at the GRPS |

Suction Lines at the GRPS |

Administration Building APWRF |

Administration Building APWRF |

Interior of the Admin Building APWRF |

Interior of the Admin Building APWRF |

Oxidatin Ditch APWRF |

Effluent PS APWRF |

Admin Building APWRF |

Maintenance Building APWRF |

Digester and Rotary Drum Thickener APWRF |

Electrical Building APWRF |

RAS/WAS Pump Station APWRF |

Headworks APWRF |

Headworks APWRF |

RAS/WAS PS APWRF |

Headworks APWRF |

Electrical Building 2 APWRF |

Maintenance Building APWRF |

Mainteance Building APWRF |

Oxidation Ditch APWRF |

Maintenance Building APWRF |

RAS/WAS PS APWRF |

Electrical Building APWRF |

Digester and Rotary Drum Thickener APWRF |

Forms for Generator Pad at the Garniers Re-Pump Station |

Forms for Generator Pad at the Garniers Re-Pump Station |

Forms for Generator Pad at the Garniers Re-Pump Station |

Forms for Generator Pad at the Garniers Re-Pump Station |

Forms for Generator Pad at the Garniers Re-Pump Station |

Forms for Generator Pad at the Garniers Re-Pump Station |

Forms for Generator Pad at the Garniers Re-Pump Station |

Installing Rigid Insulation and Cement Board in Electrical Room of the Garniers Re-Pump Station |

Form for MCC Pad |

MCC at the Garniers Re-Pump Station |

Form for the MCC at the Garniers Re-Pump Station |

Pouring Concrete for Generator Pad at the Garniers Re-pump Station |

Pouring Concrete for Generator Pad at the Garniers Re-pump Station |

Pouring Concrete for Generator Pad at the Garniers Re-pump Station |

Pouring Concrete for Generator Pad at the Garniers Re-pump Station |

Pouring Concrete for Generator Pad at the Garniers Re-pump Station |

Pouring Concrete for Generator Pad at the Garniers Re-pump Station |

Pouring Concrete for Generator Pad at the Garniers Re-pump Station |

Pouring Concrete for Generator Pad at the Garniers Re-pump Station |

Grouting Pad for MCC at the Garniers Re-Pump Station |

Grouting Pad for MCC at the Garniers Re-Pump Station |

Finishing Concrete for Generator Pad at the Garniers RE-Pump Station |

Grouting Pad for MCC at the Garniers Re-Pump Station |

Grouting Pad for MCC at the Garniers Re-Pump Station |

Generator Pad for the Garniers Re-Pump Station |

Forming Pads for Pumps 2 and 3 at the Garniers Re-Pump Station |

Forming Pads for Pumps 2 and 3 at the Garniers Re-Pump Station |

Installing Insulation and Cement Board in the Electrical Room of the Garniers Re-Pump Station |

Installing Insulation and Cement Board in the Electrical Room of the Garniers Re-Pump Station |

Installing Insulation and Cement Board in the Electrical Room of the Garniers Re-Pump Station |

Forms for Pumps 2 and 3 |

Completed Pads for Pumps 2 and 3 at the garniers Re-Pump Station |

Installing Insulation and Cement Board in the Electrical Room of the Garniers Re-Pump Station |

Plug Valves for Pumps 2 and 3 at the Garniers Re-Pump Station |

Check Valves for Pumps 2 and 3 at the Garniers Re-Pump Station |

Mechanical Louvers at the Garniers Re-pump |

Discharge Piping at the Sanitary Lift Station Arbennie Pritchett WRF |

Discharge Piping at the Sanitary Lift Station Arbennie Pritchett WRF |

Discharge Piping at the Sanitary Lift Station Arbennie Pritchett WRF |

Headworks APWRF |

Headworks APWRF |

Oxidation Ditch 2 |

Setting Modular Forms at the Headworks APWRF |

Administration Building APWRF |

Column Supports for Centrifuge APWRF |

Motor Controls APWRF |

Motor Controls APWRF |

Motor Controls APWRF |

Motor Controls APWRF |

Electrical Building 1 APWRF |
Setting Electrical Duct Bank
|

Rotary Drum Thickener APWRF |

Effluent Pump Station APWRF |

Maintenance Building APWRF |

HVAC Installation APWRRF |
 |

HVAC Duct Work APWRF |

Rotary Drum Thickener APWRF |

Maintenance Building APWRF |

RAS/WAS Pump Station APWRF |

Valve and Tee at the Garniers Re-Pump Station |

Exhaust Fans Garniers Re-pump Station |

Exhaust Fans Garniers Re-pump Station |

Setting Grid for Ceiling Tile Garniers Re-pump Station |

Setting Forms for Pump Pad Garniers Re-pump Station |

Setting Forms for Pump Pad Garniers Re-pump Station |

Valve Assembly Garniers Re-pump Station |

Setting Pump Garniers Re-pump Station |

Pad for MCC |

Motor Control as Delivered Garniers Re-pump Station |

Inlets to Exhaust Fans Garniers Re-pump Station |

Setting Check Valve Garniers Re-pump Station |

MCC Pad |

Setting Check Valve Garniers Re-pump Station |

Installing Gutters Garniers Re-pump Station |

Entrance Garniers Re-pump station |

Setting Discharge Piping Garniers RE-pump Station |

Setting Discharge Piping Garniers Re-pump Station |

Motor Controls Garniers Re-pump Station |

Exterior Work Garniers Re-pump Station |
 |

Motor Controls Garniers Re-pump Station |

Electrical and Cable Ducting at Garniers Re-pump Station |

Cable Pull Box Garniers Re-pump Station |

Re-working Pump Pad Garniers Re-pump Station |

Ceiling Grid Installation Garniers RE-pump Station |

Gutters Installed Garniers Re-pump Station |

20” Plug Valve Garniers Re-pump Station |

Constantine Discusses Re-pump Controls with OCWS |

Constantine Discusses Re-pump Station Controls with OCWS |

Administration Building Arbennie Pritchett WRF |

Administration Building Arbennie Pritchett WRF |

Effluent Lines from Clarifiers Arbennie Pritchett WRF |

Running Electrical to Effluent Pump station Arbennie Pritchett WRF |

Blowers Arbennie Pritchett WRF |

Blower Skid at APWRF |

UV Disinfection Channel and Effluent Pump Station |

Headworks |

Headworks |

Forming Pista Grit Removal Channels |

Aerator Platform Oxidation Ditch APWRF |

Headworks |

Headworks |

Upper Deck Construction Oxidation Ditch APWRF |

RAS/WAS Pump Station |

RAS/WAS Pump Station |

Electrical Building #2 |

Administration Building |

Maintenance Building APWRF |

Oxidation Ditch Upper Deck Construction APWRF |

Maintenance Building APWRF |

Electrical Pull Box |

Electrical Conduit to Effluent Pump Station APWRF |
|

Exhaust Louvers at the Garniers Re-Pump Station |

Pipe Trench at the Garniers Re-Pump Station |

Interior of Garniers Re-Pump Station |

Installing Flowserve Pump at the Garniers Re-Pump Station |

Framing for Sheetrock at the Entrance to the Garniers Re-Pump Station |

Pads for Motor Controls at the Garniers Re-Pump Station |

Grounding Wire Trench at Garniers Re-Pump Station |

Louvered Exhaust |

AC System at the Garniers Re-Pump |

Flowserve Pump at the Garniers Re-Pump Station |

Installing the Grounding Wire Around the Garniers Re-Pump Station |

One of the Flowserve Pumps at the Garniers Re-pump Station |

Setting on of the Flowserve Pumps at he Garniers Re-pump Station |

Setting One of the Flow Serve Pumps at the Garniers Re-pump Station |

The Administration Building at the Arbennie Pritchett WRF |

Working on the Digester at the Arbennie Pritchett WRF |

Admin Building |

Lab Drains in the Admin Building |

Aluminum Frame for Sheet Rock Walls Administration Building |

Aluminum Framing for Sheetrock Walls Admin Building |

Aluminum Frame for Sheetrock Walls Admin Building |

Aluminum Frame for Sheetrock Walls |

Electrical Duct Bank from Electrical Building #1 |

Clarifier #1 |

Pouring Blower Pad |

Blower Pad |

Installation of 36” Effluent Line from Clarifier #1 to UV Disinfection chamber |

Pouring Blower Pad |

Pouring Blower Pad |

Pouring Blower Pad |

Motor Controls Electrical Building #1 |

Control Panel |

Pad for Motor Control Center MCC |

HVAC Duct Work |

Electrical Duct Bank Construction |

Transformer at Electrical Building #2 |

Motor Control Center at Electrical Building #2 |

Motor Control Center at Electrical Building #2 |

Motor Control Center |

Headworks |

Squirrel Transport
|
|
|
|