Weekly Updates
Week of September 9, 2007
- Engineering design from 75 to 90% complete.
- RIBs
- The County has completed excavating RIBs 13, 14, 15, 16, and 17.
- This week the County finished excavating Ribs 14 and 13. Started excavating RIB 18.
- Backfilled and completed RIBs 8 and parts of 7 and 9.
- The large diameter and branch piping for RIBs 15 and 16 are complete
- This week the large diameter and branch piping for RIB 17 was on going and about 40 percent was completed.
- Resumed installation of 30" diameter force main between RIBs 8 and 7.