Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending October 27, 2007

Arbennie WRF

  • Digester – Started shotcrete for interior wall. Rebar in progress.
  • BNR Basins – Completed rough grading for subgrade.
  • Clarifiers – Completed rough grading for subgrade.
  • Received 100% drawings.

RIBS

  • Finished piping RIB 13.
  • Placed 152 LF of 48” Concrete Pipe.
  • Continue rough grading for ribs 10, 6 and 5.
  • Placed additional 30” pipe between Ribs 7 & 8.
  • That’s all folks.

 

« Previous week's update

« Return to Weekly Update Index

© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group