Weekly Updates
Week ending October 27, 2007
Arbennie WRF
- Digester – Started shotcrete for interior wall. Rebar in progress.
- BNR Basins – Completed rough grading for subgrade.
- Clarifiers – Completed rough grading for subgrade.
- Received 100% drawings.
RIBS
- Finished piping RIB 13.
- Placed 152 LF of 48” Concrete Pipe.
- Continue rough grading for ribs 10, 6 and 5.
- Placed additional 30” pipe between Ribs 7 & 8.
- That’s all folks.
« Previous week's update
« Return to Weekly Update Index |