Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending November 3, 2007

Arbennie WRF

  • CDM (General)
    • Continues to prepare bid packages for equipment procurement
  • Precon (Sub)
    • Shotcrete concrete for inner digester wall was completed this week. 
    • Excavated for center feed piping for Clarifiers
  • NWF (Sub)
    • Excavating storm retention pond.
    • Completed access and temporary roads
  • Contractor Submittals
    • Submittal received to be reviewed:
      • Precast/Prestressed Oxidation Ditch shop drawings
    • Submittal received for information only:
      • Precon design calculations for the Digester, Clarifiers and Oxidation Ditches
    • CDM Submittal Review Transmittal received:
      • Shotcrete submittal - Approved

RIBS

  • Resumed 48” Storm drain piping (352 LF)
  • Stripping RIBS 1 through 5
  • Backfilling RIBS 4 and 5

 