Weekly Updates
Week ending November 3, 2007
Arbennie WRF
- CDM (General)
- Continues to prepare bid packages for equipment procurement
- Precon (Sub)
- Shotcrete concrete for inner digester wall was completed this week.
- Excavated for center feed piping for Clarifiers
- NWF (Sub)
- Excavating storm retention pond.
- Completed access and temporary roads
- Contractor Submittals
- Submittal received to be reviewed:
- Precast/Prestressed Oxidation Ditch shop drawings
- Submittal received for information only:
- Precon design calculations for the Digester, Clarifiers and Oxidation Ditches
- CDM Submittal Review Transmittal received:
- Shotcrete submittal - Approved
RIBS
- Resumed 48” Storm drain piping (352 LF)
- Stripping RIBS 1 through 5
- Backfilling RIBS 4 and 5