Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending November 10, 2007

Arbennie WRF

  • CDM (General)
    • Continues to prepare bid packages for equipment procurement
  • Precon (Sub)
    • Placed concrete mud slab for 42” feed pipe for Clarifier No. 1
    • Excavated footings for Oxidation Ditch Number 1.
  • NWF (Sub)
    • Continued to excavate and backfill for the storm water retention pond.

RIBS

  • OCWS Construction
    • Continue to excavate and backfill for RIBS 1 thru 5.
    • Gallet and Associates on site to verify percolation rates in RIBS 6 and 7.
    • Placed additional 30” DIP for RIBS 9 thru 18.
    • Prepared for 14” tie ins to accommodate the operation of existing spray field while the new plant is under construction

GARNIERS RE-PUMP STATION

  • Design Meeting Held in Tampa Office of HDR to review 90% design drawings

 