Weekly Updates
Week ending November 10, 2007
Arbennie WRF
- CDM (General)
- Continues to prepare bid packages for equipment procurement
- Precon (Sub)
- Placed concrete mud slab for 42” feed pipe for Clarifier No. 1
- Excavated footings for Oxidation Ditch Number 1.
- NWF (Sub)
- Continued to excavate and backfill for the storm water retention pond.
RIBS
- OCWS Construction
- Continue to excavate and backfill for RIBS 1 thru 5.
- Gallet and Associates on site to verify percolation rates in RIBS 6 and 7.
- Placed additional 30” DIP for RIBS 9 thru 18.
- Prepared for 14” tie ins to accommodate the operation of existing spray field while the new plant is under construction
GARNIERS RE-PUMP STATION
- Design Meeting Held in Tampa Office of HDR to review 90% design drawings