Weekly Updates
Week ending December 1, 2007
Arbennie WRF
- NWF
- Working on North and East access roads.
- Amtek Electric
- Temporary site electric in progress
- Grounding around digesters
- Precon
- Ox Ditches
- Erected membranes and rebar for ox ditches
- Clarifiers
- Placed concrete for 42" concrete encasements at both clarifiers 1 and 2
- Install 42" plug to hydrostatically lean test the 42" influent piping to clarifier 1
- Digester
- Received and placed thimbles in inner digester wall
- CDM
- Continued to prepare procurement packages for General, Mechanical and Electrical contract
- OCWS Construction (RIBS)
- Continue to install additional 30" piping that will feed ribs 10 thru 18
« Previous week's update
« Return to Weekly Update Index |