Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending December 8, 2007

Arbennie WRF

  • Pre Con
    • Digester
      • Pre Con installed thimbles for the sluice gates.
      • Pre Con placed concrete shotcrete for the inside of the inner wall.
      • Amtek installed grounding grid.
    • Clarifier 1
      • Placed concrete encasement for 42” influent line.
      • Hydrostatically tested the 42” influent line.
      • Started backfilling around 42” influent line.
    • Clarifier 2
      • Placed 42” influent line and placed the first lift of the concrete encasement,
    • Ox Ditch 1
      • Erected diaphragm, placed rebar and concrete footing for the west wall.
      • Erected scaffolding and diaphragm for the east wall.
    • Ox Ditch 2
      • Erected scaffolding and diaphragm for the east wall.
  • CDM
    • Continues to prepare bid packages for the Major Process Equipment.
    • Submitted bid packages to General Contractors.
  • OCWS Construction (RIBS)
    • Continue to install additional 30” piping that will feed ribs 10 thru 18

 