Arbennie WRF
- Pre Con
- Digester
- Pre Con installed thimbles for the sluice gates.
- Pre Con placed concrete shotcrete for the inside of the inner wall.
- Amtek installed grounding grid.
- Clarifier 1
- Placed concrete encasement for 42” influent line.
- Hydrostatically tested the 42” influent line.
- Started backfilling around 42” influent line.
- Clarifier 2
- Placed 42” influent line and placed the first lift of the concrete encasement,
- Ox Ditch 1
- Erected diaphragm, placed rebar and concrete footing for the west wall.
- Erected scaffolding and diaphragm for the east wall.
- Ox Ditch 2
- Erected scaffolding and diaphragm for the east wall.
- CDM
- Continues to prepare bid packages for the Major Process Equipment.
- Submitted bid packages to General Contractors.
- OCWS Construction (RIBS)
- Continue to install additional 30” piping that will feed ribs 10 thru 18