Arbennie WRF

  • Pre Con
    • Digesters
      • Placed concrete cap around digesters.
      • Begin to pre-stress interior digester wall.
    • Ox Ditches
      • Placed shotcrete for both the west and east walls.
    • Clarifiers
      • Completed backfilling and compacting sub-grade for Clarifier 1.
      • Placed concrete encasement for both 42” influent and 18” RAS lines for Clarifier 2.
      • Hydrostatically tested both of the 42” and 18” lines for Clarifier 2.
      • Started backfilling and compacting sub-grade for Clarifier 2.
  • CDM
    • General
      • Continues to prepare procurement packages from the various subcontractors, i.e., Mechanical, Architectural, Structural, and Electrical.
      • CDM’s safety director on site to address any deficiencies with CDM and subcontractors regarding safety.

RIBS

  • OCWS Construction Crews
    • County personnel continue to self perform the construction of ribs 2 through 3. The majority of the earthwork for ribs 1, 4 thru 18 is complete.
    • Resumed installation of rib piping for ribs 11 and 12.

 