Weekly Updates
Week ending December 15, 2007
Arbennie WRF
- Pre Con
- Digesters
- Placed concrete cap around digesters.
- Begin to pre-stress interior digester wall.
- Ox Ditches
- Placed shotcrete for both the west and east walls.
- Clarifiers
- Completed backfilling and compacting sub-grade for Clarifier 1.
- Placed concrete encasement for both 42” influent and 18” RAS lines for Clarifier 2.
- Hydrostatically tested both of the 42” and 18” lines for Clarifier 2.
- Started backfilling and compacting sub-grade for Clarifier 2.
- CDM
- General
- Continues to prepare procurement packages from the various subcontractors, i.e., Mechanical, Architectural, Structural, and Electrical.
- CDM’s safety director on site to address any deficiencies with CDM and subcontractors regarding safety.
RIBS
- OCWS Construction Crews
- County personnel continue to self perform the construction of ribs 2 through 3. The majority of the earthwork for ribs 1, 4 thru 18 is complete.
- Resumed installation of rib piping for ribs 11 and 12.