Arbennie WRF
- Pre Con
- Digesters
- Placed additional layer of shotcrete over tendons in inner digester ring wall.
- Ox Ditches
- Placement of shotcrete for the exterior walls of Ox ditch number 1 is on going.
- As a result of high winds, the eastern most outside wall (diaphragm only) for Ox Ditch number 2 collapsed. No one was on site, no injuries.
- Placement of rebar and forms for western outside footings.
- Clarifiers
- Continued placement of rebar and forms for both Clarifier Number 1 and 2 base slabs.
- CDM
- Continues to prepare procurement packages from the various subcontractors, i.e., Mechanical, Architectural, Structural, and Electrical.
RIBS
- OCWS Construction Crews
- Excavation and grading for rib 3 was resumed and is near completion.
- RIB piping for rib 18 is near completion.