Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending January 5, 2008

Arbennie WRF

  • Pre Con
    • Digesters
      • Placed additional layer of shotcrete over tendons in inner digester ring wall.
    • Ox Ditches
      • Placement of shotcrete for the exterior walls of Ox ditch number 1 is on going.
      • As a result of high winds, the eastern most outside wall (diaphragm only) for Ox Ditch number 2 collapsed. No one was on site, no injuries.
      • Placement of rebar and forms for western outside footings.
    • Clarifiers
      • Continued placement of rebar and forms for both Clarifier Number 1 and 2 base slabs.
  • CDM
    • Continues to prepare procurement packages from the various subcontractors, i.e., Mechanical, Architectural, Structural, and Electrical.

RIBS

  • OCWS Construction Crews
    • Excavation and grading for rib 3 was resumed and is near completion.
    • RIB piping for rib 18 is near completion.

 