Week ending January 12, 2008
Arbennie WRF
- Pre Con
- Digesters
- Completed pre-stressed inner ring wall.
- Ox Ditches
- Shotcrete for the exterior walls of Ox ditch number 1 is on going.
- Rebar and forms in progress for western outside footings.
- Shotcrete for the exterior walls of Ox ditch number 1 is in progress.
- Clarifiers
- Placed about 400 yds of concrete for both Clarifier Number 1 and 2 base slabs.
- CDM
- Received procurement packages from the various subcontractors, i.e., Civil/Mechanical, and Electrical. Architectural/ Building bids will be received this week.
RIBS
- OCWS Construction Crews
- Excavation and backfill for all 18 ribs is complete.
- RIB piping for rib 18 is finished.
- Started Rib piping for RIB Number 9.
- Two of the OFF Road Dump Trucks were demobilized.