Weekly Updates

Week ending January 12, 2008

Arbennie WRF

  • Pre Con
    • Digesters
      • Completed pre-stressed inner ring wall.
    • Ox Ditches
      • Shotcrete for the exterior walls of Ox ditch number 1 is on going.
      • Rebar and forms in progress for western outside footings.
      • Shotcrete for the exterior walls of Ox ditch number 1 is in progress.
    • Clarifiers
      • Placed about 400 yds of concrete for both Clarifier Number 1 and 2 base slabs.
  • CDM
    • Received procurement packages from the various subcontractors, i.e., Civil/Mechanical, and Electrical. Architectural/ Building bids will be received this week.

RIBS

  • OCWS Construction Crews
    • Excavation and backfill for all 18 ribs is complete.
    • RIB piping for rib 18 is finished.
    • Started Rib piping for RIB Number 9.
    • Two of the OFF Road Dump Trucks were demobilized.

 