Weekly Updates
Week ending February 2, 2008
Arbennie WRF
- Pre Con
- Digesters
- Erected diaphragm for outer ring wall.
- Ox Ditches
- Applied shotcrete to outside walls of Oxidation Ditches
- Continued Placement vapor barrier and reinforcing steel for Oxidation ditch 2 base slab. Also placed concrete encasement for 8” drain line.
- Clarifiers
- Applied shotcrete to wall for Clarifier #1.
- Applied shotcrete to wall for Clarifier #2.
- CDM
- Weekly progress meeting was held with CDM and OCWS.
- Continue to negotiate and procure subcontractors.
RIBS
- OCWS Construction Crews
- Finished rib piping for RIB Number 10.
- Placed 30” rib piping for 7.