Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending February 16, 2008

Arbennie WRF

  • NWF
    • Entrance Road and Parking
      • Grading in progress

  • Pre Con
    • Digesters
      • Application of shotcrete layers to outer wall continues
    • Ox Ditches
      • Applied shotcrete to outside walls of Oxidation Ditches
      • Continued Placement vapor barrier and reinforcing steel for Oxidation Ditch 1 base slab. Installed 42” MLSS Line
      • Installed 8” drain line ad 42” MLSS line for Oxidation Ditch # 2
      • Grading for base slab of Oxidation Ditch # 2
    • Clarifiers
      • Applied shotcrete to wall for Clarifier #1. Forms for interior launder in progress.
      • Applied shotcrete to wall for Clarifier #2.
  • CDM
    • Kick off Meeting with RDT, Coltin Electric, Lord and Sons to discuss sub contractor roles and responsibilities

RIBS

  • OCWS Construction Crews
    • Completed all of the 30” DIP for the RIB Piping, i.e., RIBS 1 thru 18.
    • Placed 8” rib piping for ribs 7 and 8.
    • Started to finish grade ribs 12 thru 18.

 

« Previous week's update

« Return to Weekly Update Index

 
© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group