Weekly Updates
Week ending February 23, 2008
Arbennie WRF
- General
- There was significant rainfall during this week which impeded progress to some extent.
- NWF
- Entrance Road and Parking
- Fill and backfill for eastern road and admin parking area in progress.
- Pre Con
- Digesters
- Construction of outer wall continues
- Ox Ditches
- Ox Ditch #1 - Rebar for base slab continues. Concrete for 42” MLSS was placed. Addressing wash out areas from this past weeks rains.
- Ox Ditch #2 - Rebar for base slab continues. Concrete for 42” MLSS was placed. Addressing wash out areas from this past week rains.
- Clarifiers
- Clarifier #1 - Shotcrete for wall continues. Scaffolds and forms for inside launder in progress.
- Clarifier #2 - Shotcrete for wall continues. Scaffolds and forms for inside launder in progress.
- CDM
- Monthly progress meeting was held with Constantine and OCWS staff this past week.
RIBS
- OCWS Construction Crews
- Installing cross drains between RIBS 12 and 18.
- Placed 8” rib piping for ribs 6 and 5.
- Continues to finish grade ribs 12 thru 18.