Week ending March 1, 2008
Arbennie WRF
- Coltin Electric
- Mobilized as the electrical sub for the project
- NWF
- Entrance Road and Parking
- Fill .and backfill for eastern road and admin parking area
- Pre Con
- Digester
- Placed concrete filet inside inner wall.
- Oxidation Ditches
- Ox Ditch #1
- Placement of rebar for base slab
- Hydrostatic testing of 42" RAS/WAS line
- Subsequently placed and additional lift of concrete for the encasement
- Repaired washouts from last week's rains
- Ox Ditch #2
- Placement of rebar for base slab
- Repaired washouts from last week's rains
- Clarifiers
- Clarifier #1 - Placed concrete slab for launder
- Clarifier #2 - Placed concrete cap for wall. Scaffold and forms for inside launder in progress.
RIBS
- OCWS Construction Crews
- Installation of cross drains between RIBs 2 and 12.
- Placed 8" RIB piping for RIBs 3 and 4
- Continue grading RIBs 12 through 18
- Coordination meeting was held to discuss the installation of the new air lines.