Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending March 1, 2008

Arbennie WRF

  • Coltin Electric
    • Mobilized as the electrical sub for the project

  • NWF
    • Entrance Road and Parking
      • Fill .and backfill for eastern road and admin parking area

  • Pre Con
    • Digester
      • Placed concrete filet inside inner wall.
    • Oxidation Ditches
      • Ox Ditch #1
        • Placement of rebar for base slab
        • Hydrostatic testing of 42" RAS/WAS line
        • Subsequently placed and additional lift of concrete for the encasement
        • Repaired washouts from last week's rains
      • Ox Ditch #2
        • Placement of rebar for base slab
        • Repaired washouts from last week's rains
    • Clarifiers
      • Clarifier #1 - Placed concrete slab for launder
      • Clarifier #2 - Placed concrete cap for wall. Scaffold and forms for inside launder in progress.
  • CDM
    • Weekly Meetings

RIBS

  • OCWS Construction Crews
    • Installation of cross drains between RIBs 2 and 12.
    • Placed 8" RIB piping for RIBs 3 and 4
    • Continue grading RIBs 12 through 18
    • Coordination meeting was held to discuss the installation of the new air lines.

 

« Previous week's update

« Return to Weekly Update Index

 