Week ending March 8, 2008

Arbennie WRF

  • Coltin Electric
    • installing conduit for primary feeds.
  • RDT
    • Mobilized on site
  • Lord and Sons
    • Mobilized on site
  • NWF
    • Entrance Road and Parking
      • Grading for Maintenance and Admin Building in Progress
  • Pre Con
    • Digester
      • Placed concrete filet inside inner wall
    • Oxidation Ditches
      • Oxidation Ditch #1
        • Placement of rebar for base slab
        • Backfilling for 42" RAS/WAS line
      • Oxidation Ditch #2
        • Placement of rebar for base slab
        • Backfilling for 42" RAS/WAS line
    • Clarifiers
      • Clarifier #1 - Pre-stressed exterior walls. Placement of shotcrete for exterior layer.
      • Clarifier #2 - Placed concrete for launder. Began pre-stress of exterior walls.
  • CDM
    • Weekly Meetings

RIBS

  • OCWS Construction Crews
    • Flushed 30" and RIB 15 piping
    • Grading of RIBs 12 through 18
    • Installation of piping for RIBs 5 through 1
    • Installation of Riser Pipes for RIBs 15 and 16

 