Weekly Updates
Week ending March 8, 2008
Arbennie WRF
- Coltin Electric
- installing conduit for primary feeds.
- RDT
- Lord and Sons
- NWF
- Entrance Road and Parking
- Grading for Maintenance and Admin Building in Progress
- Pre Con
- Digester
- Placed concrete filet inside inner wall
- Oxidation Ditches
- Oxidation Ditch #1
- Placement of rebar for base slab
- Backfilling for 42" RAS/WAS line
- Oxidation Ditch #2
- Placement of rebar for base slab
- Backfilling for 42" RAS/WAS line
- Clarifiers
- Clarifier #1 - Pre-stressed exterior walls. Placement of shotcrete for exterior layer.
- Clarifier #2 - Placed concrete for launder. Began pre-stress of exterior walls.
- CDM
RIBS
- OCWS Construction Crews
- Flushed 30" and RIB 15 piping
- Grading of RIBs 12 through 18
- Installation of piping for RIBs 5 through 1
- Installation of Riser Pipes for RIBs 15 and 16
« Previous week's update
« Return to Weekly Update Index |