Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending March 15, 2008

Arbennie WRF

  • Coltin Electric
    • installing conduit for primary feeds.
  • RDT
    • Mobilized on site
  • Lord and Sons
    • Placed edge forms for footings
  • NWF
    • Grading for Maintenance and Admin Building in Progress
  • Pre Con
    • Digester
      • Set up to pre-stress outer wall
    • Oxidation Ditches
      • Oxidation Ditch #1 - Placement of rebar for base slab
      • Oxidation Ditch #2 - Placement of rebar for base slab
    • Clarifiers
      • Clarifier #1
        • Shotcrete cover coat for walls
        • Rub inside launder walls
      • Clarifier #2
        • Pre-stress exterior walls
        • Rub inside walls
        • Rub inside Launder walls
  • CDM
    • Weekly Meetings
    • Contact coordination
    • Coordination meeting for purchase of the MAXIMO software

RIBS

  • OCWS Construction Crews
    • Concrete pads for risers for RIBs 15, 16, 14
    • Placed piping for RIBs 4 and 3

 