Weekly Updates
Week ending March 22, 2008
Arbennie WRF
- Coltin Electric
- installing conduit for primary feeds for Administration Building.
- Began Placement of electrical conduits for Maintenance Building.
- RDT
- Lord and Sons
- Continued placement edge forms for footings for Administration Building.
- Placement of Edge Form Footings for Maintenance Building.
- NWF
- Finished grading for Maintenance and Admin Building in Progress.
- Pre Con
- Digester
- Completed pre-stress outer wall. Started application of final coat of shotcrete.
- Oxidation Ditches
- Oxidation Ditch #1
- Placement of rebar for base slab.
- Oxidation Ditch #2
- Placement of rebar for base slab.
- Clarifiers
- Clarifier #1
- Finished shotcrete cover coat for walls.
- Continued to Rub inside launder walls.
- Clarifier #2
- Started final coat of shotcrete for exterior wall.
- Continued to rub inside walls.
- CDM
- Monthly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Concrete pads for risers for RIBs 17.
- Placed piping for RIB 2.
- Installed Riser Piping for RIB 13.
« Previous week's update
« Return to Weekly Update Index |