Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending March 22, 2008

Arbennie WRF

  • Coltin Electric
    • installing conduit for primary feeds for Administration Building.
    • Began Placement of electrical conduits for Maintenance Building.
  • RDT
    • Idle
  • Lord and Sons
    • Continued placement edge forms for footings for Administration Building.
    • Placement of Edge Form Footings for Maintenance Building.
  • NWF
    • Finished grading for Maintenance and Admin Building in Progress.
  • Pre Con
    • Digester
      • Completed pre-stress outer wall. Started application of final coat of shotcrete.
    • Oxidation Ditches
      • Oxidation Ditch #1 - Placement of rebar for base slab.
      • Oxidation Ditch #2 - Placement of rebar for base slab.
    • Clarifiers
      • Clarifier #1
        • Finished shotcrete cover coat for walls.
        • Continued to Rub inside launder walls.
      • Clarifier #2
        • Started final coat of shotcrete for exterior wall.
        • Continued to rub inside walls.
  • CDM
    • Monthly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • Concrete pads for risers for RIBs 17.
    • Placed piping for RIB 2.
    • Installed Riser Piping for RIB 13.

 

« Previous week's update

« Return to Weekly Update Index

© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group