Week ending March 29, 2008

Arbennie WRF

  • Coltin Electric
    • installing conduit for primary feeds for Administration Building.
    • Began Placement of electrical conduits for Maintenance Building.
  • RDT
    • Idle
  • Lord and Sons
    • Maintenance Bldg
      • Installed drain lines.
      • Prepared subgrade for base slab.
    • Administration Bldg
      • Installed drain lines.
      • Prepared subgrade for base slab.
  • NWF
    • Finished grading for Maintenance and Admin Building. Started to grade for parking areas.
  • Pre Con
    • Digester
      • Final coat of shotcrete applied.
    • Oxidation Ditches
      • Oxidation Ditch #1 - Placement of rebar for base slab.
      • Oxidation Ditch #2 - Placement of rebar for base slab.
    • Clarifiers
      • Clarifier #1
        • Cleaned out scaffolding.
        • Prepared forms for exterior cap.
      • Clarifier #2
        • Cleaned out scaffolding.
        • Prepared forms for exterior cap.
  • CDM
    • Monthly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • Completed all underground RIB Piping!!!!!
    • Installed Riser Piping for RIBs 10, 11, and 12.

 