Arbennie WRF
- Coltin Electric
- installing conduit for primary feeds for Administration Building.
- Began Placement of electrical conduits for Maintenance Building.
- RDT
- Lord and Sons
- Maintenance Bldg
- Installed drain lines.
- Prepared subgrade for base slab.
- Administration Bldg
- Installed drain lines.
- Prepared subgrade for base slab.
- NWF
- Finished grading for Maintenance and Admin Building. Started to grade for parking areas.
- Pre Con
- Digester
- Final coat of shotcrete applied.
- Oxidation Ditches
- Oxidation Ditch #1
- Placement of rebar for base slab.
- Oxidation Ditch #2
- Placement of rebar for base slab.
- Clarifiers
- Clarifier #1
- Cleaned out scaffolding.
- Prepared forms for exterior cap.
- Clarifier #2
- Cleaned out scaffolding.
- Prepared forms for exterior cap.
- CDM
- Monthly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Completed all underground RIB Piping!!!!!
- Installed Riser Piping for RIBs 10, 11, and 12.