Weekly Updates
Week ending April 5, 2008
Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons.
- RDT
- Excavation for ultraviolet light disinfection system.
- Lord and Sons
- Maintenance Bldg
- Prepared sub-grade for base slab
- Administration Bldg
- Continued preparation of the foundation sub-grade.
- NWF
- Finished grading for eastern access road and parking areas.
- Pre Con
- Digester
- Setting of rebar and forms for rotorary drum thickener elevated slab.
- Oxidation Ditches
- Oxidation Ditch #1 – Poured the concrete for the base slab, 654 cu yds.
- Oxidation Ditch #2 – Continued placement of rebar for base slab.
- Clarifiers
- Clarifier #1
- Final cleanup of construction or pre-stressed structure.
- Clarifier #2
- Final cleanup of construction or pre-stressed structure.
- CDM
- Monthly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Installed Riser Piping for RIBs 7, 8, and 9.
« Previous week's update
« Return to Weekly Update Index |