Arbennie WRF

  • Coltin Electric
    • Performed electrical work for Lord and Sons.
  • RDT
    • Excavation for ultraviolet light disinfection system.
  • Lord and Sons
    • Maintenance Bldg
      • Prepared sub-grade for base slab
    • Administration Bldg
      • Continued preparation of the foundation sub-grade.
  • NWF
    • Finished grading for eastern access road and parking areas.
  • Pre Con
    • Digester
      • Setting of rebar and forms for rotorary drum thickener elevated slab.
    • Oxidation Ditches
      • Oxidation Ditch #1 – Poured the concrete for the base slab, 654 cu yds.
      • Oxidation Ditch #2 – Continued placement of rebar for base slab.
    • Clarifiers
      • Clarifier #1
        • Final cleanup of construction or pre-stressed structure.
      • Clarifier #2
        • Final cleanup of construction or pre-stressed structure.
  • CDM
    • Monthly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • Installed Riser Piping for RIBs 7, 8, and 9.

 