Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending April 12, 2008

Arbennie WRF

  • Coltin Electric
    • Performed electrical work for Lord and Sons.
  • RDT
    • Excavation for ultraviolet light disinfection system.
  • Lord and Sons
    • Maintenance Bldg
      • Placement of rebar for foundations slab.
    • Administration Bldg
      • Placement of rebar for foundations slab.
  • NWF
    • Backfill and grading of southeast access road.
  • Pre Con
    • Digester
      • Setting of rebar and forms for rotorary drum thickener elevated slab.
    • Oxidation Ditches
      • Oxidation Ditch #1 – Erection of diaphram for end walls.
      • Oxidation Ditch #2 – Placed 645 cubic yards of concrete for base slab.
    • Clarifiers
      • Clarifier #1
        • Structure complete.
      • Clarifier #2
        • Structure complete.
  • CDM
    • Monthly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • Concrete splash pads for RIBs 7 through 18.
    • Installed riser pipes 6, 7, 8 and 9.
    • Installation of air supply tubing in progress.

 

« Previous week's update

« Return to Weekly Update Index