Weekly Updates
Week ending April 12, 2008
Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons.
- RDT
- Excavation for ultraviolet light disinfection system.
- Lord and Sons
- Maintenance Bldg
- Placement of rebar for foundations slab.
- Administration Bldg
- Placement of rebar for foundations slab.
- NWF
- Backfill and grading of southeast access road.
- Pre Con
- Digester
- Setting of rebar and forms for rotorary drum thickener elevated slab.
- Oxidation Ditches
- Oxidation Ditch #1 – Erection of diaphram for end walls.
- Oxidation Ditch #2 – Placed 645 cubic yards of concrete for base slab.
- Clarifiers
- Clarifier #1
- Clarifier #2
- CDM
- Monthly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Concrete splash pads for RIBs 7 through 18.
- Installed riser pipes 6, 7, 8 and 9.
- Installation of air supply tubing in progress.