Weekly Updates
Week ending April 19, 2008
Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons on maintenance and administration buildings.
- RDT
- Ultraviolet Disinfection Chamber
- Installed dewatering equipment and began to erect the forms for the base slab.
- Headworks
- Began excavation for footings.
- Lord and Sons
- Maintenance Bldg
- Continued placement of rebar for foundations slab.
- Administration Bldg
- Continued placement of re-bar for foundation slab.
- NWF
- Backfill and grading of southeast access road.
- Pre Con
- Digester
- Continued setting of rebar and forms for rotorary drum thickener elevated slab.
- Oxidation Ditches
- Oxidation Ditch #1 – Setting or reinforcing steel for end walls.
- Oxidation Ditch #2 – Setting or reinforcing steel for end walls.
- Clarifiers
- Clarifier #1 -
Structure complete.
- Clarifier #2
- Structure complete.
- CDM
- Monthly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Concrete splash pads for RIBs 2 through 7.
- Completed installation of riser pipes.
- Completed installation of air supply tubing in progress.
- Initiated terminations of air supply lines inside junction boxes.
- Placement of rock for access road.
Garniers Re-pump Station
- Speegle Construction
- Awarded Bid
- Finalizing contract documents
Garniers WWTF De-Commissioning
- Board of County Commissioners
« Previous week's update
« Return to Weekly Update Index |