Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons
- RDT
- Effluent Pump Station
- Continued erection of forms for effluent pump station base slab.
- Headworks
- Continued excavation for footings.
- Clarifiers
- Clarifier # 1- Installing Baffles.
- Clarifier # 2- Installing Baffles.
- Lord and Sons
- Maintenance Bldg
- Continued placement of rebar for foundations slab.
- Pest Control Application
- Administration Bldg
- Continued placement of re-bar for foundation slab.
- Pest Control Application
- NWF
- Backfill and grading of north access road.
- Pre Con
- Digester
- Continued setting of rebar and forms for rotorary drum thickener elevated slab.
- Oxidation Ditches
- Oxidation Ditch #1 – Began shotcrete application to end walls.
- Oxidation Ditch #2 – Began shotcrete application to end walls.
- CDM
- Monthly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Concrete splash pads for the remaining RIBs were placed.
- Installed by-pass line to retention pond.
- Completed installation of air supply tubing in progress.
- Terminations inside of junction boxes of air supply lines continues.
- Continued placement of rock for access road.
Garniers Re-pump Station
- Speegle Construction
- Finalizing contract documents