Arbennie WRF

  • Coltin Electric
    • Performed electrical work for Lord and Sons
  • RDT
    • Effluent Pump Station
      • Continued erection of forms for effluent pump station base slab.
    • Headworks
      • Continued excavation for footings.
    • Clarifiers
      • Clarifier # 1- Installing Baffles.
      • Clarifier # 2- Installing Baffles.
  • Lord and Sons
    • Maintenance Bldg
      • Continued placement of rebar for foundations slab.
      • Pest Control Application
    • Administration Bldg
      • Continued placement of re-bar for foundation slab.
      • Pest Control Application
  • NWF
    • Backfill and grading of north access road.
  • Pre Con
    • Digester
      • Continued setting of rebar and forms for rotorary drum thickener elevated slab.
    • Oxidation Ditches
      • Oxidation Ditch #1 – Began shotcrete application to end walls.
      • Oxidation Ditch #2 – Began shotcrete application to end walls.
  • CDM
    • Monthly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • Concrete splash pads for the remaining RIBs were placed.
    • Installed by-pass line to retention pond.
    • Completed installation of air supply tubing in progress.
    • Terminations inside of junction boxes of air supply lines continues.
    • Continued placement of rock for access road.

Garniers Re-pump Station

  • Speegle Construction
    • Finalizing contract documents

 

« Previous week's update

« Return to Weekly Update Index

© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group