Weekly Updates
Week ending May 3, 2008
Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons
- RDT
- UV Channel / Effluent Pump Station
- Continued erection of forms for effluent pump station walls.
- Placed Concrete for base slab.
- Headworks
- Clarifiers
- Clarifier # 1- Continued Installing Baffles.
- Clarifier # 2- Completed installation of Weirs and Baffles.
- Lord and Sons
- Maintenance Bldg
- Forms for foundations slab ready for concrete.
- Administration Bldg
- Continued placement of re-bar for foundation slab.
- NWF
- Continued backfill and grading of north access road.
- Pre Con
- Digester
- Continued setting of rebar and forms for rotorary drum thickener elevated slab.
- Oxidation Ditches
- Oxidation Ditch #1 – Continued shotcrete application to end walls.
- Oxidation Ditch #2 – Continued shotcrete application to end walls.
- CDM
- Monthly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Completed concrete splash pads.
- Terminations inside of junction boxes of air supply lines continues.
- Continued placement of rock for access road.
Garniers Re-pump Station
- Speegle Construction
- Finalizing contract documents
« Previous week's update
« Return to Weekly Update Index |