Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending May 10, 2008

Arbennie WRF

  • Coltin Electric
    • Performed electrical work for Lord and Sons
  • RDT
    • UV Channel / Effluent Pump Station
      • Placed forms for effluent pump station walls.
      • Placed Concrete for effluent pump station walls, lower elevation.
    • Headworks
      • Backfilled for footings.
    • Clarifiers
      • Clarifier # 1- Continued Installing Baffles.
      • Clarifier # 2- Completed installation of Weirs and Baffles.
  • Lord and Sons
    • Maintenance Bldg
      • Placed concrete for the first ½ of the base slab.
    • Administration Bldg
      • Continued placement of re-bar for foundation slab.
    • Electrical Building
      • Prepared subgrade and set forms for foundation.
  • NWF
    • Continued backfill and grading of north access road.
  • Pre Con
    • Digester
      • Continued setting of rebar and forms for rotorary drum thickener elevated slab.
    • Oxidation Ditches
      • Oxidation Ditch #1 – Continued shotcrete application to end walls.
      • Oxidation Ditch #2 – Continued shotcrete application to end walls.
  • CDM
    • Monthly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • Grading of RIB Berms
    • Continued placement of rock for access road.

Garniers Re-pump Station

  • Speegle Construction
    • Mobilization.

 