Arbennie WRF

  • Coltin Electric
    • Performed electrical work for Lord and Sons.
    • Installed conduit penetrations for digester.
  • RDT
    • UV Channel / Effluent Pump Station
      • No work.
    • Headworks
      • Placed forms and rebar for base slab.
    • Clarifiers
      • Clarifier # 1- Completed installation of Weirs and Baffles.
      • Clarifier # 2- Idle.
  • Lord and Sons
    • Maintenance Bldg
      • Placed concrete for the second ½ of the base slab.
    • Administration Bldg
      • Set up for concrete.
    • Electrical Building
      • Placed re-bar and forms for foundation.
  • NWF
    • Completed grading of north access road.
  • Pre Con
    • Digester - No Work.
    • Oxidation Ditches
      • Oxidation Ditch #1 – Continued shotcrete application to end walls.
      • Oxidation Ditch #2 – Continued shotcrete application to end walls.
  • CDM
    • Monthly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • Completed grading of RIB Berms
    • Continued placement of rock for access road.
    • Installing Concrete headwalls.

Garniers Re-pump Station

  • Speegle Construction
    • Mobilization.

 