Weekly Updates
Week ending May 17, 2008
Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons.
- Installed conduit penetrations for digester.
- RDT
- UV Channel / Effluent Pump Station
- Headworks
- Placed forms and rebar for base slab.
- Clarifiers
- Clarifier # 1- Completed installation of Weirs and Baffles.
- Clarifier # 2- Idle.
- Lord and Sons
- Maintenance Bldg
- Placed concrete for the second ½ of the base slab.
- Administration Bldg
- Electrical Building
- Placed re-bar and forms for foundation.
- NWF
- Completed grading of north access road.
- Pre Con
- Digester
- No Work.
- Oxidation Ditches
- Oxidation Ditch #1 – Continued shotcrete application to end walls.
- Oxidation Ditch #2 – Continued shotcrete application to end walls.
- CDM
- Monthly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Completed grading of RIB Berms
- Continued placement of rock for access road.
- Installing Concrete headwalls.
Garniers Re-pump Station