Weekly Updates
Week ending May 24, 2008
Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons.
- Installed conduit penetrations for digester.
- RDT
- UV Channel / Effluent Pump Station
- Leak test for wet well and channel. Installed damp proofing and initiated backfill.
- Headworks
- Installed buried piping and placed concrete for base slab.
- Clarifiers
- Clarifier # 1- Completed installation of Weirs and Baffles.
- Clarifier # 2- Idle.
- State Civil
- Installed Yard piping 1.e, potable and fire lines
- Lord and Sons
- Maintenance Bldg
- Administration Bldg
- Completed placement of concrete for foundation slab.
- Electrical Building
- Installed conduit in base slab.
- Placed concrete for base slab.
- Pre Con
- Digester
- No Work.
- Oxidation Ditches
- Oxidation Ditch #1 – Forms for Top Cap in Progress.
- Oxidation Ditch #2 – Forms for Top Cap in Progress.
- CDM
- Monthly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Completed grading of RIB Berms
- Continued placement of rock for access road.
- Installing Concrete headwalls.
Garniers Re-pump Station
- Speegle Construction
- Excavated and placed forms for concrete pipe trench.