Weekly Updates
Week ending June 7, 2008
Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons.
- RDT
- UV Channel / Effluent Pump Station
- Headworks
- Poured 2nd section of Headworks base slab
- Clarifiers
- Clarifier # 1- Idle.
- Clarifier # 2- Idle.
- RAS/WAS Pump Station
- Placed underground piping and concrete pipe encasement
- Placed forms, rebar, and concrete for the bottom of the wet well channel
- State Civil
- Continue installing potable water and fire lines
- Lord and Sons
- Maintenance Bldg
- Administration Bldg
- Placed and poured grout for first bond beam of 8” CMU walls.
- Electrical Building
- Installation of electrical conduit for base slab.
- Pre Con
- Digester
- Oxidation Ditches
- Oxidation Ditch #1 – Began erecting diaphragm for interior wall.
- Oxidation Ditch #2 – Began erecting diaphragm for interior wall.
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Grading and seeding continues
- Continued placement of rock for access road.
- Installing Concrete headwalls.
Garniers Re-pump Station
- Speegle Construction
- Continued installing rebar for pipe trench base slab
- Weekly meeting with Speegle.
« Previous week's update