Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending June 14, 2008

Arbennie WRF

  • Coltin Electric
    • Performed electrical work for Lord and Sons.
  • RDT
    • UV Channel / Effluent Pump Station
      • Idle
    • Headworks
      • Placed concrete for the mid section of the base slab
    • Clarifiers
      • Clarifier # 1- Idle.
      • Clarifier # 2- Idle.
    • RAS/WAS Pump Station
      • Placed forms, rebar, and concrete for the wet well walls.
    • State Civil
      • Continue installing yard piping i.e., potable and fire lines
  • Lord and Sons
    • Maintenance Bldg
      • Placement of 8” CMU walls
    • Administration Bldg
      • Continued to place and grout 8” CMU wall
    • Electrical Building
      • Removed forms for Generator Pad
      • Installed conduit in base slab.
  • Pre Con
    • Digester
      • Idle.
    • Oxidation Ditches
      • Oxidation Ditch #1
        • Shotcrete interior walls.
        • Preparation for pre-stressing.
      • Oxidation Ditch #2
        • Shotcrete interior walls.
        • Preparation for pre-stressing.
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • Grading and seeding continues.
    • Installing Concrete headwalls.

Garniers Re-pump Station

  • Speegle Construction
    • Placed 56 cu yds of concrete for trench slab and erected forms and rebar.
    • Weekly meeting with Speegle.

 

« Previous week's update

« Return to Weekly Update Index

© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group