Week ending June 14, 2008
Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons.
- RDT
- UV Channel / Effluent Pump Station
- Headworks
- Placed concrete for the mid section of the base slab
- Clarifiers
- Clarifier # 1- Idle.
- Clarifier # 2- Idle.
- RAS/WAS Pump Station
- Placed forms, rebar, and concrete for the wet well walls.
- State Civil
- Continue installing yard piping i.e., potable and fire lines
- Lord and Sons
- Maintenance Bldg
- Placement of 8” CMU walls
- Administration Bldg
- Continued to place and grout 8” CMU wall
- Electrical Building
- Removed forms for Generator Pad
- Installed conduit in base slab.
- Pre Con
- Digester
- Oxidation Ditches
- Oxidation Ditch #1
- Shotcrete interior walls.
- Preparation for pre-stressing.
- Oxidation Ditch #2
- Shotcrete interior walls.
- Preparation for pre-stressing.
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Grading and seeding continues.
- Installing Concrete headwalls.
Garniers Re-pump Station
- Speegle Construction
- Placed 56 cu yds of concrete for trench slab and erected forms and rebar.
- Weekly meeting with Speegle.