Weekly Updates
Week ending June 28, 2008
Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons.
- RDT
- UV Channel / Effluent Pump Station
- Poured Slab at elevation 64.75
- Headworks
- Removed Forms for West Wall.
- Clarifiers
- Clarifier # 1- Idle.
- Clarifier # 2- Idle.
- RAS/WAS Pump Station
- Placed walls for RAS WAS Pump Station
- State Civil
- Continue installing yard piping i.e., potable and fire lines
- Pre Con
- Oxidation Ditch 1
- Pre-stress of exterior wall complete.
- Apply Shotcrete to interior walls.
- Oxidation Ditch 2
- Applying Shotcrete to interior walls
- Setting up for pre-stressing of exterior walls.
- Lord and Sons
- Maintenance Bldg
- Placement of 8” CMU walls
- Administration Bldg
- Continued to place and grout 8” CMU wall
- Electrical Building
1
- Placing forms for base slab
- Installing conduit in base slab.
- Electrical Building 2
- Placing forms for base slab.
- Installing conduit in base slab.
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
- OCWS Construction Crews
- Removing forms for concrete head walls.
- RIBS are near completion.
Garniers Re-pump Station
- Speegle Construction
- Continue to erect the forms and rebar for the trench walls.
- Held weekly meeting with Speegle
- Submittal review is ongoing