Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending June 28, 2008

Arbennie WRF

  • Coltin Electric
    • Performed electrical work for Lord and Sons.
  • RDT
    • UV Channel / Effluent Pump Station
      • Poured Slab at elevation 64.75
    • Headworks
      • Removed Forms for West Wall.
    • Clarifiers
      • Clarifier # 1- Idle.
      • Clarifier # 2- Idle.
    • RAS/WAS Pump Station
      • Placed walls for RAS WAS Pump Station
    • State Civil
      • Continue installing yard piping i.e., potable and fire lines
  • Pre Con
    • Oxidation Ditch 1
      • Pre-stress of exterior wall complete.
      • Apply Shotcrete to interior walls.
    • Oxidation Ditch 2
      • Applying Shotcrete to interior walls
      • Setting up for pre-stressing of exterior walls.
  • Lord and Sons
    • Maintenance Bldg
      • Placement of 8” CMU walls
    • Administration Bldg
      • Continued to place and grout 8” CMU wall
    • Electrical Building 1
      • Placing forms for base slab
      • Installing conduit in base slab.
    • Electrical Building 2
      • Placing forms for base slab.
      • Installing conduit in base slab.
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • Removing forms for concrete head walls.
    • RIBS are near completion.

Garniers Re-pump Station

  • Speegle Construction
    • Continue to erect the forms and rebar for the trench walls.
    • Held weekly meeting with Speegle
    • Submittal review is ongoing

 

« Previous week's update

« Return to Weekly Update Index

© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group