Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending July 12, 2008

Arbennie WRF

  • Coltin Electric
    • Performed electrical work for Lord and Sons.
  • RDT
    • UV Channel / Effluent Pump Station
      • Wall construction continues. 60% of base slabs complete.
    • Headworks
      • Slab is complete. Wall and column construction continues.
    • Clarifiers
      • Clarifier # 1- Idle.
      • Clarifier # 2- Idle.
    • RAS/WAS Pump Station
      • Walls and slab construction continues at RAS/WAS pump station.
    • Site Civil
      • Sanitary sewer line installation.
  • Pre Con
    • Digester
      • Idle
    • Oxidation Ditch 1
      • Pre-stress of exterior wall complete.
      • Applying Shotcrete to interior walls.
    • Oxidation Ditch 2
      • Finished pre-stressing of exterior walls.
  • Lord and Sons
    • Maintenance Bldg
      • 8” CMU wall complete.
      • Placement of tie beams
    • Administration Bldg
      • 8" CMU Wall complete.
      • Placement of tie beams.
    • Electrical Building 1
      • Initiated 8" CMU Wall construction.
    • Electrical Building 2
      • Idle.
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • RIBS complete.

Garniers Re-pump Station

  • Speegle Construction
    • Stripped forms on north trench wall
    • Backfill of trenches.
    • Continue to hold weekly progress meetings.

 

« Previous week's update

« Return to Weekly Update Index

© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group