Weekly Updates
Week ending July 12, 2008
Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons.
- RDT
- UV Channel / Effluent Pump Station
- Wall construction continues. 60% of base slabs complete.
- Headworks
- Slab is complete. Wall and column construction continues.
- Clarifiers
- Clarifier # 1- Idle.
- Clarifier # 2- Idle.
- RAS/WAS Pump Station
- Walls and slab construction continues at RAS/WAS pump station.
- Site Civil
- Sanitary sewer line installation.
- Pre Con
- Digester
- Oxidation Ditch 1
- Pre-stress of exterior wall complete.
- Applying Shotcrete to interior walls.
- Oxidation Ditch 2
- Finished pre-stressing of exterior walls.
- Lord and Sons
- Maintenance Bldg
- 8” CMU wall complete.
- Placement of tie beams
- Administration Bldg
- 8" CMU Wall complete.
- Placement of tie beams.
- Electrical Building
1
- Initiated 8" CMU Wall construction.
- Electrical Building 2
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Stripped forms on north trench wall
- Backfill of trenches.
- Continue to hold weekly progress meetings.