Weekly Updates
Week ending July 19, 2008
Arbennie WRF
- Coltin Electric
- Performed electrical work for Lord and Sons.
- RDT
- UV Channel / Effluent Pump Station
- Wall construction continues. 60% of base slabs complete.
- Headworks
- Slab is complete. Wall and column construction continues.
- Clarifiers
- Clarifier # 1- Idle.
- Clarifier # 2- Idle.
- RAS/WAS Pump Station
- Continue wall and slab construction.
- Site Civil
- Sanitary sewer line installation.
- Pre Con
- Digester
- Oxidation Ditch 1
- Complete grounding
- Covertcoat exterior walls
- Construct interior walls
- Oxidation Ditch 2
- Complete grounding
- Covercoat exterior walls
- Construct interior walls
- Lord and Sons
- Maintenance Bldg
- Continue to place 8” CMU walls.
- Placement of tie beams
- Administration Bldg
- Electrical Building
1
- Initiated 8" CMU Wall construction.
- Electrical Building 2
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Prepared Forms for Base Slab of Re-Pump Station.
- Continue to hold weekly progress meetings.