Weekly Updates
Week ending July 26, 2008
Arbennie WRF
- Coltin Electrical
- Performed electrical work for Lord and Sons.
- RDT
- UV Channel / Effluent Pump Station
- Base Slab Complete
- Wall construction continues
- Headworks
- Wall and column construction continues.
- Clarifiers
- Clarifier # 1-Idle.
- Clarifier # 2- Idle. Two pieces of baffle ready to be installed.
- RAS/WAS Pump Station
- Continue wall construction.
- Site Civil
- Sanitary sewer line installation.
- Pre Con
- Digester
- Oxidation Ditch 1
- Cover coat complete
- Construction of interior walls
- Oxidation Ditch 2
- Cover coat complete
- Construction of interior walls
- Lord and Sons
- Maintenance Bldg
- Continue to place 8” CMU walls.
- Administration Bldg
- Electrical Building
1
- Continued 8" CMU Wall construction.
- Electrical Building 2
- Conduit installation complete.
- Form SOG
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Prepared Forms for Base Slab of Re-Pump Station.
- Installation of electrical conduit
- Continue to hold weekly progress meetings.