Arbennie WRF

  • Coltin Electrical
    • Performed electrical work for Lord and Sons.
  • RDT
    • UV Channel / Effluent Pump Station
      • Exterior Wall Construction is Complete
      • Interior Wall and Deck Construction in Progress
    • Centrifuge Roll Off Slab
      • Form and Pour Slab.
      • Setting of Steel Plates
    • Headworks
      • Grouting Headworks Walls
    • Clarifiers
      • Clarifier # 1-Clarifier Mechanism is being installed.
      • Clarifier # 2- Clarifier Mechanism is being installed
    • RAS/WAS Pump Station
      • Idle.
    • Site Civil
      • Sanitary sewer line installation.
  • Pre Con
    • Digester
      • Idle
    • Oxidation Ditch 1
      • Construction of interior walls
    • Oxidation Ditch 2
      • Construction of interior walls
  • Lord and Sons
    • Maintenance Bldg
      • Tie Beams Under Construction.
    • Administration Bldg
      • Tie Beams Under Construction.
    • Electrical Building 1
      • Form and Pour Tie Beam
      • Skid Mounted Generator was set.
    • Electrical Building 2
      • CMU Walls Under Construction
      • Skid Mounted Generator was set.
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • RIBS complete.

Garniers Re-pump Station

  • Speegle Construction
    • Construction of Base Slab.
    • Installation of electrical conduit complete
    • Continue to hold weekly progress meetings.