Weekly Updates
Week ending August 30, 2008
Arbennie WRF
- Coltin Electrical
- Performed electrical work for Lord and Sons.
- RDT
- UV Channel / Effluent Pump Station
- Centrifuge Roll Off Slab
- Headworks
- Clarifiers
- Clarifier # 1-Clarifier Mechanism is being installed.
- Clarifier # 2- Clarifier Mechanism is being installed
- RAS/WAS Pump Station
- Deck and Wall Construction
- Site Civil
- Connect sanitary lines to on-site pump station.
- Connect 42" from Headworks to Aeration Basins.
- Pre Con
- Digester
- Oxidation Ditch 1
- Construction of interior walls
- Begin to Set Platform
- Oxidation Ditch 2
- Construction of interior walls
- Begin to Set Platform
- Lord and Sons
- Maintenance Bldg
- Tie Beams Under Construction.
- Administration Bldg
- Tie Beams Under Construction.
- Electrical Building
No 1
- Form and pour tie beam
- Skid Mounted Generator was set.
- Electrical Building No 2
- CMU Walls Under Construction
- Skid Mounted Generator was set.
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Continue Block Work
- Block work began.
- Installation of mechanical chase line
- Continue to hold weekly progress meeting
- Formed transformer pad. Installing mechanical chase lines.