Weekly Updates
Week ending September 06, 2008
Arbennie WRF
- Coltin Electrical
- Performed electrical work for Lord and Sons.
- RDT
- UV Channel / Effluent Pump Station
- Centrifuge Roll Off Slab
- Headworks
- Column Construction Continues
- Clarifiers
- Clarifier # 1-Clarifier Mechanism Installation Completed.
- Clarifier # 2- Clarifier Mechanism Installation Completed.
- RAS/WAS Pump Station
- Deck and Wall Construction Continues
- Site Civil
- Connect sanitary lines to on site pump station
- Connect 42” from Headworks to Aeration Basins
- Pre Con
- Digester
- Oxidation Ditch 1
- Construction of interior walls continues
- Setting Platform
- Oxidation Ditch 2
- Construction of interior walls continues
- Setting Platform
- Lord and Sons
- Maintenance Bldg
- Tie Beams Under Construction
- Application of Roof Damp proofing
- Administration Bldg
- Tie Beams Under Construction
- Application of Roof Damp proofing
- Electrical Building
No 1
- Tie beam Complete
- Application of Roof Damp proofing
- Electrical Building No 2
- Tie Beam Complete
- Application of Roof Damp proofing
- CDM
- Weekly Progress Meeting
- Subcontractor Coordination
RIBS
Garniers Re-pump Station
- Speegle Construction
- Continue Block Work
- Installation of mechanical chase line
- Continue to hold weekly progress meeting