Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending September 20, 2008

Arbennie WRF

  • Coltin Electrical
    • Performed electrical work for Lord and Sons.
  • RDT
    • UV Channel / Effluent Pump Station
      • Idle
    • Centrifuge Roll Off Slab
      • Idle
    • Headworks
      • Column, Wall, and Trough Construction Continues
    • Clarifiers
      • Clarifier # 1- Idle
      • Clarifier # 2- Idle.
    • RAS/WAS Pump Station
      • Deck and Wall Construction Continues
    • Site Civil
      • Install 42"/36" DI Pipe from Clarifiers to UV/Effluent Pump Station.
      • Installation of pumps at the On-Site Sanitary Lift Station
  • Pre Con
    • Digester
      • Continue Installation of Air Piping
    • Oxidation Ditch 1
      • Construction of interior walls continues
      • Setting Platform
    • Oxidation Ditch 2
      • Construction of interior walls continues
      • Setting Platform
  • Lord and Sons
    • Maintenance Bldg
      • Installation of Roof Trusses
    • Administration Bldg
      • Pouring Concrete for Beams and Columns
    • Electrical Building No 1
      • Tie Beam Complete.
      • Application of Roof Damp proofing
    • Electrical Building No 2
      • Tie Beam Complete.
      • Application of Roof Damp proofing
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • RIBS complete.

Garniers Re-pump Station

  • Speegle Construction
    • Completed Masonry
    • Installed Bridge Crane
    • Installation of mechanical chase line
    • Continue to hold weekly progress meeting

« Previous week's update

« Return to Weekly Update Index

© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group