Week ending October 4, 2008
Arbennie WRF
- Coltin Electrical
- Performed electrical work for Lord and Sons.
- RTD
- UV Channel / Effluent Pump Station
- Centrifuge Roll Off Slab
- Headworks
- Form and Pour Walls and Decks
- Clarifiers
- Clarifier # 1- Idle
- Clarifier # 2- Idle.
- RAS/WAS Pump Station
- Form and Pour Walls and Columns
- Site Civil
- Installation of Sanitary Lines North of Basin
- Pre Con
- Digester
- Continue Installation of Air Piping
- Form and Pour Blower Slab
- Oxidation Ditch 1
- Construction of interior walls continues
- Setting Platform
- Oxidation Ditch 2
- Construction of interior walls continues
- Setting Platform
- Lord and Sons
- Maintenance Bldg
- Administration Bldg
- Installation of Roof Trusses and Blocking
- Electrical Building
No 1
- Form and Pour Equipment Pads
- Electrical Building No 2
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Installation of Metal Roofing Panels
- Form Electrical Equipment Pads
- Continue to hold weekly progress meeting