Weekly Updates
Week ending October 18, 2008
Arbennie WRF
- Coltin Electrical
- Performed electrical work for Lord and Sons.
- RTD
- UV Channel / Effluent Pump Station
- Centrifuge Roll Off Slab
- Form and Pour Columns for Centrifuge
- Headworks
- Form and Pour Walls and Decks
- Clarifiers
- Clarifier # 1- Idle
- Clarifier # 2- Idle.
- RAS/WAS Pump Station
- Form and Pour Walls and Columns
- Site Civil
- Installation of or 42" and 36" from Clarifiers to UV Chamber
- Installation of 8" Sanitary Line from Manhole 3 to Manhole 4
- Pre Con
- Digester
- Continue Installation of Air Piping
- Placement of rotary Drum Thickener onto Platform
- Oxidation Ditch 1
- Construction of interior walls continues
- Setting Platform
- Oxidation Ditch 2
- Construction of interior walls continues
- Setting Platform
- Lord and Sons
- Maintenance Bldg
- Begin Placement of Split Face Block
- Rough-in HVAC
- Pour Canopy Slab
- Administration Bldg
- Installation of Metal Roofing
- Install Metal Studs for Drywall
- Rough-in HVAC
- Placement of Split Face Block
- Electrical Building
No 1
- Installation of Transformer
- Install Split Face Block
- Install Motor Control Center (MCC) continued
- Install Split Face Block
- Electrical Building No 2
- Installation of Transformer
- Install Split Face Block
- Install MCCs
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Continue Standing Seam Roof installation Less Facia
- Begin Placement of Facia
- Placement of Exhaust Fan Pads
- Placement of Piping in Trenches
- Pour Electrical Equipment Pads
- Continue to hold weekly progress meeting
« Previous week's update
« Return to Weekly Update Index |