Weekly Updates
Week ending October 25, 2008
Arbennie WRF
- Coltin Electrical
- Performed electrical work for Lord and Sons.
- RTD
- UV Channel / Effluent Pump Station
- Centrifuge Roll Off Slab
- Headworks
- Form and Pour Walls and Decks
- Clarifiers
- Clarifier # 1- Idle
- Clarifier # 2- Idle.
- RAS/WAS Pump Station
- Form and Pour Walls and Columns
- Site Civil
- Installation of or 42" and 36" from Clarifiers to UV Chamber
- Pre Con
- Digester
- Continue Installation of Air Piping
- Oxidation Ditch 1
- Oxidation Ditch 2
- Lord and Sons
- Maintenance Bldg
- Continue Placement of Split Face Block
- Rough-in HVAC
- Administration Bldg
- Installation of Metal Roofing, Insulation and plywood.
- Completed Metal Studs for Drywall
- Rough-in HVAC and Electric
- Continue Placement of Split Face Block
- Electrical Building
No 1
- Install Motor Control Center (MCC) continued
- Electrical Building No 2
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Pumps Delivered
- Exhause fans being installed
- Electrical Overhead Rough-in
- Begin Installation of Z-furring
- Continue to hold weekly progress meeting