Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending October 25, 2008

Arbennie WRF

  • Coltin Electrical
    • Performed electrical work for Lord and Sons.
  • RTD
    • UV Channel / Effluent Pump Station
      • Idle
    • Centrifuge Roll Off Slab
      • Idle
    • Headworks
      • Form and Pour Walls and Decks
    • Clarifiers
      • Clarifier # 1- Idle
      • Clarifier # 2- Idle.
    • RAS/WAS Pump Station
      • Form and Pour Walls and Columns
    • Site Civil
      • Installation of or 42" and 36" from Clarifiers to UV Chamber
  • Pre Con
    • Digester
      • Continue Installation of Air Piping
    • Oxidation Ditch 1
      • Form Mixer Platforms
    • Oxidation Ditch 2
      • Form Mixer Platforms
  • Lord and Sons
    • Maintenance Bldg
      • Continue Placement of Split Face Block
      • Rough-in HVAC
    • Administration Bldg
      • Installation of Metal Roofing, Insulation and plywood.
      • Completed Metal Studs for Drywall
      • Rough-in HVAC and Electric
      • Continue Placement of Split Face Block
    • Electrical Building No 1
      • Install Motor Control Center (MCC) continued
    • Electrical Building No 2
      • Install MCCs
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • RIBS complete.

Garniers Re-pump Station

  • Speegle Construction
    • Pumps Delivered
    • Exhause fans being installed
    • Electrical Overhead Rough-in
    • Begin Installation of Z-furring
    • Continue to hold weekly progress meeting

« Previous week's update

« Return to Weekly Update Index

© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group