Weekly Updates

Week ending November 8, 2008

Arbennie WRF

  • Coltin Electrical
    • Performed electrical work for Lord and Sons.
  • RTD
    • UV Channel / Effluent Pump Station
      • Idle
    • Centrifuge Roll Off Slab
      • Strip Column Forms
    • Headworks
      • Form and Pour Walls and Decks
    • Clarifiers
      • Clarifier # 1- Idle
      • Clarifier # 2- Idle.
    • RAS/WAS Pump Station
      • Form and Pour Walls, Columns and Deck
    • Site Civil
      • Install WAS Line to Digester
      • Install Piping at Plant Lift Station
  • Pre Con
    • Digester
      • Continue Installation of Air Piping and Diffusers
    • Oxidation Ditch 1
      • Form and Pour Mixer Platforms
    • Oxidation Ditch 2
      • Form and Pour Mixer Platforms
  • Lord and Sons
    • Maintenance Bldg
      • Continue Placement of Split Face Block
      • Rough-in Plumbing, HVAC, and Electric
    • Administration Bldg
      • Completed Placement of Split Face Block
      • Rough-in Plumbing and HVAC
    • Electrical Building No 1
      • Install Motor Control Center (MCC) continued
    • Blower Pad
      • Install Blowers and Piping
    • Electrical Building No 2
      • Installation of MCCs Continues
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • RIBS complete.

Garniers Re-pump Station

  • Speegle Construction
    • Installed Gutters, Install Fan Flashing
    • Form and Pour Pump Pads
    • Set Pumps
    • Install Suction and Discharge Piping