Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending November 15, 2008

Arbennie WRF

  • Coltin Electrical
    • Performed electrical work for Lord and Sons.
  • RTD
    • UV Channel / Effluent Pump Station
      • Pour grout at Reuse Pumps
    • Centrifuge Roll Off Slab
      • Strip Column Forms
    • Headworks
      • Form and Pour Walls and Decks
    • Clarifiers
      • Clarifier # 1- Idle
      • Clarifier # 2- Idle.
    • RAS/WAS Pump Station
      • Form and Pour Walls, Columns and Deck
    • Site Civil
      • Install Sanitary Sewer North of Aeration Basins
      • Completed RAS Line from RAS/WAS to Headworks
      • Install Electrical Duct Bank from EB1 to UV/EFF PS
  • Pre Con
    • Digester
      • Continue Installation of Air Piping and Diffusers
      • Install Handrails
    • Oxidation Ditch 1
      • Form and Pour Mixer Platforms
    • Oxidation Ditch 2
      • Form and Pour Mixer Platforms
  • Lord and Sons
    • Maintenance Bldg
      • Continue Placement of Split Face Block
      • MEP Rough-In
    • Administration Bldg
      • Completed Placement of Split Face Block
      • MEP Rough-In
    • Electrical Building No 1
      • Install PLC
      • Begin Split Face Block Placement
    • Electrical Building No 2
      • Install PLC
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • RIBS complete.

Garniers Re-pump Station

  • Speegle Construction
    • Form and Pour Generator Pad
    • Installed Mechanical Louvers
    • Form and Pour Pump Pads 2 and 3
    • Installed Rigid Insulation and Cement Board in Electrical Room

« Previous week's update

« Return to Weekly Update Index

© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group