Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending November 22, 2008

Arbennie WRF

  • Coltin Electrical
    • Performed electrical work for Lord and Sons.
  • RTD
    • UV Channel / Effluent Pump Station
      • Idle
    • Centrifuge Roll Off Slab
      • Idle
    • Headworks
      • Form and Pour Walls and Decks
    • Clarifiers
      • Clarifier # 1- Idle
      • Clarifier # 2- Idle.
    • RAS/WAS Pump Station
      • Form and Pour Walls, Columns and Deck
    • Site Civil
      • Install reuse water line and RAS line at the RAS/WAS Pump Station
  • Pre Con
    • Digester
      • Interior Air Piping Installation Complete
      • Handrails and Stairs Installed
    • Oxidation Ditch 1
      • Form and Pour Mixer Platforms
    • Oxidation Ditch 2
      • Form and Pour Mixer Platforms
  • Lord and Sons
    • Maintenance Bldg
      • Continue Placement of Split Face Block
      • MEP Rough-In Continues
      • Roof Trim and Standing Seam Roof Installation in Progress
    • Administration Bldg
      • MEP Rough-In Continues
      • Roof Trim and Standing Seam Roof Installation in Progress
    • Electrical Building No 1
      • Split Face Block Installation Continues
      • Install Roof Trim
    • Electrical Building No 2
      • Install Roof Trim
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • RIBS complete.

Garniers Re-pump Station

  • Speegle Construction
    • Installation of Suction and Discharge Lines Continues
    • Generator Delivered and Installed
    • Textured Finish Applied to Electrical Room Walls
    • Removed North Fence

« Previous week's update

« Return to Weekly Update Index

© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group