Weekly Updates
Week ending November 22, 2008
Arbennie WRF
- Coltin Electrical
- Performed electrical work for Lord and Sons.
- RTD
- UV Channel / Effluent Pump Station
- Centrifuge Roll Off Slab
- Headworks
- Form and Pour Walls and Decks
- Clarifiers
- Clarifier # 1- Idle
- Clarifier # 2- Idle.
- RAS/WAS Pump Station
- Form and Pour Walls, Columns and Deck
- Site Civil
- Install reuse water line and RAS line at the RAS/WAS Pump Station
- Pre Con
- Digester
- Interior Air Piping Installation Complete
- Handrails and Stairs Installed
- Oxidation Ditch 1
- Form and Pour Mixer Platforms
- Oxidation Ditch 2
- Form and Pour Mixer Platforms
- Lord and Sons
- Maintenance Bldg
- Continue Placement of Split Face Block
- MEP Rough-In Continues
- Roof Trim and Standing Seam Roof Installation in Progress
- Administration Bldg
- MEP Rough-In Continues
- Roof Trim and Standing Seam Roof Installation in Progress
- Electrical Building
No 1
- Split Face Block Installation Continues
- Install Roof Trim
- Electrical Building No 2
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Installation of Suction and Discharge Lines Continues
- Generator Delivered and Installed
- Textured Finish Applied to Electrical Room Walls
- Removed North Fence