Week ending December 6, 2008
Arbennie WRF
- Coltin Electrical
- Performed electrical work for Lord and Sons.
- RTD
- UV Channel / Effluent Pump Station
- Centrifuge Roll Off Slab
- Formed and poured elevated deck.
- Headworks
- Form and Pour Walls and Decks
- Clarifiers
- Clarifier # 1- Idle
- Clarifier # 2- Idle.
- RAS/WAS Pump Station
- Site Civil
- Pre Con
- Digester
- Interior Air Piping Installation Complete
- Handrails and Stairs Installed
- Oxidation Ditch 1
- Form and Pour Mixer Platforms
- Oxidation Ditch 2
- Form and Pour Mixer Platforms
- Lord and Sons
- Maintenance Bldg
- Begin to install window sills, windows, roof trim, and start drywall.
- Administration Bldg
- Rough-in HVAC and Electric
- Begin to install window sills, windows, roof trim, and start drywall
- Electrical Building
No 1
- Split Face Block Installation Continues
- Install Roof Trim
- Electrical Building No 2
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Begin yard piping by-pass
- Install duct work.
- Paint interior of pump house
- Field measure for steel grating
- Installed main control panel, pulled fiber, installed switch gear, begin VFD installation
OCWS Collection and Transmissions System Improvements
- Installed tapping saddles and valves, pressure tested and tapped north and south 20" sewage force mains.
- Installed line stop fittings, pressure tested and tapped both line stops on south 20" sewage forcemain