Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending January 3, 2009

Arbennie WRF

  • Coltin Electrical
    • Performed electrical work for Lord and Sons.
  • RTD
    • Septage Receiving Station
      • Form pad.
    • UV Channel/Effluent Pump Station
      • Idle
    • Centrifuge Roll Off Slab
      • Idle
    • Headworks
      • Idle
    • Clarifiers
      • Clarifier # 1- Idle
      • Clarifier # 2- Idle.
    • RAS/WAS Pump Station
      • Form and Pour Walls.
    • Site Civil
      • Pipe testing
  • Pre Con
    • Digester
      • Idle
    • Oxidation Ditch 1
      • Form and Pour Mixer and Aerator Platforms
    • Oxidation Ditch 2
      • Form and Pour Mixer and Aerator Platforms
  • Lord and Sons
    • Maintenance Bldg
      • Pulled wire
      • Continue drywall
      • Install standing seam roof ridge caps.
    • Administration Bldg
      • Pulled wire
      • Continue drywall
      • Install standing seam roof ridge caps.
    • Electrical Building No 1
      • Install Roof Ridge Cap
      • Install electrical equipment and HVAC
    • Electrical Building No 2
      • Install Roof Ridge Cap
      • Install Electrical Equipment
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.

RIBS

  • OCWS Construction Crews
    • RIBS complete.

Garniers Re-pump Station

  • Speegle Construction
    • Continued yard piping and compaction testing
    • Pressure Test both suction and discharge piping.
    • Grout in pump and motors
    • Set doors and frames
    • Forming pipe pedestals
    • Begin site work (retention basin)

OCWS Collection and Transmissions System Improvements

  • EA Services

« Previous week's update

« Return to Weekly Update Index

 
© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group