Weekly Updates
Week ending January 3, 2009
Arbennie WRF
- Coltin Electrical
- Performed electrical work for Lord and Sons.
- RTD
- Septage Receiving Station
- UV Channel/Effluent Pump Station
- Centrifuge Roll Off Slab
- Headworks
- Clarifiers
- Clarifier # 1- Idle
- Clarifier # 2- Idle.
- RAS/WAS Pump Station
- Site Civil
- Pre Con
- Digester
- Oxidation Ditch 1
- Form and Pour Mixer and Aerator Platforms
- Oxidation Ditch 2
- Form and Pour Mixer and Aerator Platforms
- Lord and Sons
- Maintenance Bldg
- Pulled wire
- Continue drywall
- Install standing seam roof ridge caps.
- Administration Bldg
- Pulled wire
- Continue drywall
- Install standing seam roof ridge caps.
- Electrical Building
No 1
- Install Roof Ridge Cap
- Install electrical equipment and HVAC
- Electrical Building No 2
- Install Roof Ridge Cap
- Install Electrical Equipment
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Continued yard piping and compaction testing
- Pressure Test both suction and discharge piping.
- Grout in pump and motors
- Set doors and frames
- Forming pipe pedestals
- Begin site work (retention basin)
OCWS Collection and Transmissions System Improvements
« Previous week's update
« Return to Weekly Update Index |