Weekly Updates
Week ending January 17, 2009
Arbennie WRF
- Coltin Electrical
- Performed electrical work for Lord and Sons.
- RTD
- Septage Receiving Station
- UV Channel/Effluent Pump Station
- Centrifuge Roll Off Slab
- Strip elevated deck forms
- Headworks
- Concrete is complete with the exception o fbeams and grout. Equipment and grating is being installed.
- Clarifiers
- Grouting of Clarifier floor.
- RAS/WAS Pump Station
- Complete forming and pouring of walls.
- Site Civil
- Pre Con
- Digester
- Oxidation Ditch 1
- Form and Pour Center walkways
- Oxidation Ditch 2
- Form and Pour Center walkways
- Lord and Sons
- Maintenance Bldg
- Drywall Complete
- Install lighting and begin painting
- Administration Bldg
- Installed Electrical Equipment and pull and terminate wires.
- Install gutters and downspouts
- Drywall is complete.
- Electrical Building
No 1
- Install Gutters and Downspouts complete.
- Install electrical equipment and HVAC
- Electrical Building No 2
- Install Electrical Equipment
- Install Gutters and Downspouts
- CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Painting of pipes, doors and door frames.
- Install fencing.
- Install vent line coming off air release vlaves.
- Install lights in pumphouse.
- Site grading including stormwater ponds.
OCWS Collection and Transmissions System Improvements
- OCWS continues to work on interconnect piping