Weekly Updates
Week ending January 31, 2009
Arbennie WRF
- Septage Receiving Station
- UV Channel/Effluent Pump Station
- Install reuse and effluent pumps.
- Centrifuge Roll Off Slab
- Install piping. Form and pour stair landing. Install stairs and handrails.
- Headworks
- Install grid and drain piping, slide gates, and grating.
- Clarifiers
- Clarifier #1 - Idle.
- Clarifier #2 - Idle.
- RAS/WAS Pump Station
- Form and pour beams. Install RAS/WAS piping to pump pads. Form and pour pump pads.
- Site Civil
- Install RAS/WAS piping to pump pads.
- Digester
- Oxidation Ditch 1 & 2
- Point and patch concrete. Install mixers and aerators.
- Maintenance Bldg
- Pull and terminate wire.
- Install canopy, roll up doors, and HVAC equipment.
- Administration Bldg
- Pull and terminate wire.
- Install tile, ceiling grid, downspouts, and HVAC equipment.
- Electrical Building
No 1
- Electrical Building No 2
CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Grout bases of pipe supports.
- Complete steel grating installation.
- Begin site landscaping.
- Finish painting.
- Electrical: Test fire alarm. Terminate connections with VFD's/Louvers/Dampers.
- Construct canopy for false door.
OCWS Collection and Transmissions System Improvements
- OCWS continues inter connect piping at the Garniers WWTP
« Previous week's update
« Return to Weekly Update Index |