Weekly Updates
Week ending February 7, 2009
Arbennie WRF
- Septage Receiving Station
- UV Channel/Effluent Pump Station
- Install reuse and effluent pumps and piping.
- Centrifuge Roll Off Slab
- Scarify roll off pad. Form and pour stair landing. Install stairs and handrails.
- Headworks
- Point and patch concrete. Install grit equipment and piping.
- Clarifiers
- Clarifier #1 - Idle.
- Clarifier #2 - Idle.
- RAS/WAS Pump Station
- Form and pour pump pads and slab.
- Site Civil
- Install RAS/WAS piping to pump pads.
- Digester
- Install piping to rotary drum thickener and sludge feed pumps.
- Oxidation Ditch 1 & 2
- Clean out tanks. Install aerators.
- Maintenance Bldg
- Install lights and HVAC equipment.
- Administration Bldg
- Pull and terminate wire.
- Hang interior doors.
- Install lights, ceramic tile, and HVAC equipment.
- Electrical Building
No 1
- Terminate cable.
- Install ceiling grid.
- Install chemical skids.
- Electrical Building No 2
- Terminate cable
- Install ceiling grid .
CDM
- Weekly Progress Meeting.
- Subcontractor Coordination.
RIBS
Garniers Re-pump Station
- Speegle Construction
- Electrical: Install surge suppression.
- Install main entrance gate.
- Construct canopy for false door.
OCWS Collection and Transmissions System Improvements
- OCWS continues inter connect piping at the Garniers WWTP
« Previous week's update
« Return to Weekly Update Index |