Weekly Updates
Week ending February 14, 2009
Arbennie WRF
- Septage Receiving Station
- UV Channel/Effluent Pump Station
- Install reuse and effluent pumps and piping.
- Install miscellaneous metals.
- Centrifuge and Roll Off Slab
- Headworks
- Point and patch concrete.
- Install miscellaneous metals and piping.
- Clarifiers
- Clarifier #1 - Idle.
- Clarifier #2 - Idle.
- RAS/WAS Pump Station
- Point and patch concrete.
- Install RAS Pumps and piping.
- Site Civil
- Install effluent and reuse piping.
- Install scum piping.
- Digester
- Install piping to rotary drum thickener and sludge feed pumps.
- Aeration Basins 1 & 2
- Clean out tanks.
- Install aerators and air piping.
- Maintenance Building
- Install HVAC equipment.
- Install ceramic tile.
- Continue painting.
- Administration Building
- Install ceramic tile, HVAC equipment, EIFS, and folding partition.
- Continue painting.
- Electrical Building
No 1
- Terminate cable.
- Install chemical skids.
- Electrical Building No 2
- Terminate cable.
- Install ceiling grid .
CDM
- Weekly Progress Meeting
- Subcontractor Coordination
RIBS
Garniers Re-pump Station
- Speegle Construction
- Electrical: Startup and test generator.
- Install pressure gauges on trench piping.
- Complete false door canopy installation.
OCWS Collection and Transmissions System Improvements
- OCWS continues inter connect piping at the Garniers WWTP.